VOTEWISENBURGVILLAGE TRUSTEE
← All accomplishments

Modernizing Our Water System

Broke Ground on Our First Water Filtration Plant

Our Board helped move Peoria Heights’ long-term water plan into action. The Village broke ground on its first filtration plant on September 25, 2026, with treatment designed to remove iron and manganese that contribute to discolored water.

Read the supporting records

Record and sources reviewed

Opening Statement

Every home and business in Peoria Heights depends on reliable water. For years, residents have raised concerns about water quality and aging infrastructure. During my time on the Village Board, we’ve worked toward a long-term plan to address those challenges, rather than leaving each generation to face the same repairs.

Key figures and highlights

Why This Matters

For years, Peoria Heights residents have dealt with concerns about water quality and aging infrastructure. These are not problems that can be solved with a temporary repair or a short-term budget decision.

They require a plan, a financial strategy, and a commitment to doing the work.

That's why one of the most important efforts during my time on the Village Board has been developing a comprehensive, long-term approach to modernizing our water system.

The Engineering Assessment

The Village commissioned Woodard & Curran to evaluate its water system. In April 2022, the consultant and Village staff conducted a condition assessment. The resulting FY 2024–2043 Water System Capital Improvement Plan was published in February 2023.

The assessment describes a large, aging system whose treatment, supply, and distribution needs require coordinated rehabilitation and replacement rather than isolated repairs.

  • Approximately 194,000 feet of water distribution mains.
  • Approximately 149,845 feet of cast-iron mains.
  • Five groundwater supply wells.
  • Manganese-related compliance violations in 2021 and 2022, documented in the plan’s treatment recommendations.

Supporting sources

A Plan for the Next Generation

I see this as an unprecedented step forward for Peoria Heights: a long-term plan paired with the Village’s first water filtration plant. In its September 2026 project announcement, the Village described filtration as a first in the water system’s 127-year history. I’m proud our Board has helped move that work forward.

Instead of continuing to address infrastructure problems one repair at a time, the Village developed a comprehensive capital improvement plan that identifies priorities, estimates costs, and establishes a long-term schedule for investment.

The plan covers water treatment, wells, storage tanks, water mains, valves, and lead service lines. It provides a framework for making improvements in a deliberate, financially responsible way.

The plan covers FY 2024–2043, with an initial five-year priority program for FY 2024–2028. These schedules identify planned work; a plan alone does not establish that a project has been completed.

Supporting sources

Filtering Iron and Manganese for the First Time

For residents who have dealt with brown or tea-colored water, this is a particularly important part of the project. The new plant is designed to remove iron and manganese. The Village identifies manganese as a significant contributor to the discoloration residents experience. Addressing that problem is one of the reasons I’ve supported investing in filtration.

The original engineering plan made manganese treatment a priority and evaluated several approaches. The new plant takes that planning into construction. Groundbreaking took place on September 25, 2026; the plant is underway, not yet described here as operational.

I also want us to plan beyond today’s needs. The facility is designed with room for future expansion to address PFAS, often called forever chemicals. PFOS is one chemical in that broader family. This gives us a path to add treatment as needs change.

Supporting sources

Replacing Aging Water Mains

The original plan identifies Lake Avenue, Prospect Road, and Route 29 water main replacements, along with distribution system isolation valves. Replacing aging mains supports reliability, reduces the risk of failures, and helps the system perform over the long term. Isolation valves help crews isolate parts of the system during maintenance and repairs.

The figures below are the February 2023 plan’s estimates, including the engineering and construction amounts in its project schedule. They are not final bids, actual expenditures, or verified construction costs. Inclusion in the plan does not confirm current project completion.

Supporting sources

Lead Service Line Replacement

Another part of this work matters directly to household budgets. The pipe running from the service shutoff into a home is normally the property owner’s responsibility. Through the Village’s lead service line replacement program, qualifying lines are being replaced at no direct cost to the homeowner. I’m proud we’re taking that on as a community instead of leaving residents to arrange and pay for those replacements themselves.

The Village’s May 2025 program announcement explains that crews check both sides of the shutoff and fully replace the service line if either side contains lead or galvanized steel. The no-cost commitment applies to replacement through this program; it does not mean every private plumbing repair is covered or that water service itself is free.

The initial inventory referenced in the plan identified approximately 159 known lead service lines and 1,528 service lines of unknown material. This is a historical inventory, not a current count of remaining lead lines.

The initial FY 2024–2028 program included $1.702 million for lead service line inventory and replacement, under an assumed 49% principal forgiveness funding scenario. The plan sets out a systematic approach to identifying materials and replacing lead service lines.

Supporting sources

Long-Term Financial Planning

The plan evaluates financing options, including potential state and federal assistance. Its funding roadmap identifies opportunities to explore, rather than documenting awarded funding.

Pursuing outside funding is important to making improvements while minimizing unnecessary financial burdens on ratepayers. Final grants, loans, forgiveness awards, and project costs must be supported by their own records before being described as secured or spent.

Supporting sources

Continuing the Work

Water infrastructure isn't always something residents see, but it's something every household and business depends on.

The decisions we make today will affect the reliability and quality of our water system for decades. I'm proud that we've taken meaningful steps toward addressing these challenges with a comprehensive plan rather than leaving them for future generations.

Supporting Charts and Data

Filtering Iron and Manganese for the First Time

  1. April 2022

    Engineering condition assessment

    Assessment completed
    Milestone details and source

    Woodard & Curran and Village staff inspected major components of the system. This milestone concerns the assessment, not completion of infrastructure work.

    FY 2024–2043 Water System Capital Improvement Plan

    Woodard & Curran, February 2023; §§2.1–2.2, pp. 2-1–2-5 (PDF pp. 7–11)

  2. February 2023

    Long-term capital plan published

    Plan published
    Milestone details and source

    FY 2024–2043 framework, with the initial FY 2024–2028 priority program. Scheduled projects remain plans unless later records establish progress.

    Water System CIP: initial five-year program

    Appendix A, FY 2024–2028 cost schedule (PDF p. 32)

  3. September 25, 2026

    Water treatment plant groundbreaking

    Ongoing initiative
    Milestone details and source

    WCBU reported from the groundbreaking ceremony. This is a construction milestone, not evidence that the plant is complete or operational. Status reflects the source reviewed on October 15, 2026.

    WCBU: water filtration plant groundbreaking

    Joe Deacon, September 25, 2026; reporting from the ceremony

Supporting sources

Replacing Aging Water Mains

Water main replacements: February 2023 planning estimates
Planned projectEstimated cost (USD)Basis
Lake Avenue water main replacement$1,441,0002023 plan estimate; not final cost
Prospect Road water main replacement$3,004,0002023 plan estimate; not final cost
Route 29 water main replacement$2,504,0002023 plan estimate; not final cost

Supporting sources

Read the Records

Read the original water capital plan (PDF)

Supporting sources

PDFs are original source records. The FY 2018–2019 budget is scanned and may not be screen-reader accessible; the cited figures are transcribed into this page’s text and tables.

Explore the full record